High-speed connectivity on the way as over 3,600 premises in the Curragh Camp deployment area see build works commence
2,500 homes, businesses and farms in Kildare can avail of a high-speed connection today
National Broadband Ireland (NBI), the company rolling out the new high speed fibre broadband network under the Government’s National Broadband Plan (NBP) today announced that construction has commenced to deliver high-speed broadband to over 3,600 premises in the Curragh Camp deployment area in County Kildare.
In Kildare, there are approximately 16,000 premises in the Intervention Area (IA), which includes homes, farms, commercial businesses and schools. Under the National Broadband Plan, County Kildare will see an investment of €53M in the new high speed fibre network. This will enable e-learning, remote monitoring of livestock or equipment, e-health initiatives, better energy efficiency in the home, and facilitate increased levels of remote working.
Having successfully completed the Survey and Design phase of the project, 3,610 Kildare premises in the Curragh Camp deployment area are now under construction to have high-speed fibre. Homes, businesses and farms in these areas will be ready to connect to the National Broadband Network.
National Broadband Ireland’s website is regularly updated to show estimated connection dates. Signing up to the NBI email notifications at /eoi/ is the easiest way to get the most up to date status of premises during the rollout and when premises will be ready for order.
Works have already been completed in other parts of Kildare and there are approximately 2,507 premises that are available to order or pre-order high-speed, reliable broadband across the county, with 847 connections already made to the network. National Broadband Ireland is calling on people to visit nbi.ie/map/ and enter their Eircode to see if they are ready to connect.
Peter Hendrick, Chief Executive Officer, National Broadband Ireland said: “Our teams continue to work on the rollout plan and substantial progress has been made on works in Kildare.”
He continued: “We are confident that the rollout will continue to gather pace as our ability to move premises from the construction phase to the order phase ramps up. We are currently working closely with retail service providers, and other stakeholders, to connect homes in Kildare. Minimum speeds of 500Mbps will be available.
“Our mission is to end the digital divide across the country. Digital connectivity is critical to many of our activities, and this new Fibre-to-the-Home network, will be a key enabler for the sustainability of local businesses and communities.”
Under the National Broadband Plan, 559,000 premises nationwide are included in the Intervention Area, which was established by the Department of Environment, Climate and Communications to identify areas where commercial operators are not currently providing access to high-speed broadband or do not intend to.
Keep up to Speed!
NBI is encouraging people to check their eligibility and register for updates at www.nbi.ie to receive regular notifications related to their own premises as works progresses in their area.