Surveying for National Broadband Plan continues across Wexford

11th January 2021

National Broadband Ireland (NBI), the company rolling out the new high speed fibre broadband network under the Government’s National Broadband Plan (NBP) today announced that surveying works in several areas of Wexford are well underway.

Surveying
NBI contractors have been on the ground across the country for eight months and over 150,000 premises nationwide have been surveyed to date. This involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area. This will enable network design solutions for the provision of a fibre network to every premises in the Intervention Area – a map of over 544,000 premises nationwide identified by the Department of the Environment, Climate and Communication (DECC) – as not being served with adequate broadband speeds.

Wexford
In Wexford, there are 22,430 premises in the Intervention Area (IA), which includes homes, farms, commercial businesses and schools. This equates to 27% of all premises in the county. Under the National Broadband Plan, Wexford will see an investment of €88M in the new high speed fibre network. This will enable e-learning, remote monitoring of livestock or equipment, e-health initiatives, better energy efficiency in the home, and facilitate increased levels of remote working.

NBI crews have made substantial progress in Wexford, the following areas are being surveyed: Tomhaggard, Ladys Island, Broadway, Mayglass, Tagoat, Kilrane, Tacumshane, Rosslare, Rosslare Harbour, Killinick, Piercetown, Murrintown, Cleristown, Baldwinstown, Bridgetown, Duncormick, Kilmore and Kilmore Quay.

In June 2020, NBI crews started initial works for surveying in the following townlands: Oilgate, Castlebridge, Taghmon, Ballykelly, Barntown, Castle Ellis, Kilbride, Ballyhuskard, Bridgetown and Whitechurch.

All NBI contractors will also carry official ID cards and essential worker letters, and have received training on adhering to all Covid 19 guidelines. They will have vehicles, PPE and signage with both their own, and NBI logos.

Broadband Connection Points (BCPs)
In advance of the fibre to the home roll out, the NBP provides for the delivery of BCPs nationwide. Over 60 of these sites are now ‘live’ and have both internal and external broadband access. These facilities – which include GAA clubs, community centres and tourist sites – will provide free public access to high speed internet in the rollout area.

These will pave the way for rural communities to receive the benefits of broadband, from mobile working, e-learning and mobile banking, to digital tourism. A full list can be found at /bcp-map/ Primary schools in the Intervention Area are also being connected for educational access as part of the NBP. Locations of Broadband Connection Points in county Wexford will include St Mary’s GAA Complex in Rosslare, Stella Maris Community Centre, Ferrybank Leisure Centre, and Raheen Parochial House.

Progress on the ground
NBI chief executive Peter Hendrick said the company was pleased with the progress being made: “We started physical work on the ground last January and I am delighted to report that this is going very well. We are acutely aware that people want access to high speed broadband as soon as possible, and our goal is to deliver that.

“Survey designs are an important part of mapping out how every home and business will be connected, and these will provide the blueprint for how the NBI fibre is laid. The BCPs are a key milestone in delivering access to high speed internet in the Intervention Area, and we’re delighted to see these being connected for access – internally and externally – right across the county.”

NBI’s website www.nbi.ie has a search tool to enable the public to check whether their premises is within the rollout area, and to show indicative dates for areas being surveyed. There is also a facility to register for updates on this. Detailed designs for the fibre area network are drawn up following these surveys. The network build has started in parts of Cavan, Cork, Galway and Limerick, and some connections are expected by the end of this year. NBI’s contact centre can be reached at 0818 624 624 (lo-call) or contactus@nbi.ie

Latest News: Events

  • JOC June 2022
    29th June 2022

    Opening Statement by Peter Hendrick, Chief Executive Officer, National Broadband Ireland to the Joint Oireachtas Committee on Transport and Communications

    Chair, Committee Members,   Thank you for the invitation to meet with you again and the opportunity to provide a progress update on the work of National Broadband Ireland in rolling out the National Broadband Plan.  I am Peter Hendrick, Chief Executive Officer of NBI, and I am joined here today by TJ Malone, Chief Executive […]

    READ MORE
  • Imagine the future
    20th June 2022

    A “Smarter Way of Living” takes top prize at NBI “Imagine the Future” national final

    10 primary schools take home awards as creativity of “leaders of the future” hailed National Broadband Ireland (NBI), the company delivering the National Broadband Plan (NBP), today (Monday) hosted 100 primary school students, from Junior Infants to Sixth Class, at an event at the Barretstown fun camp in Kildare for the presentation of prizes to […]

    READ MORE
  • Gaeltec
    14th June 2022

    25% increase in National Broadband Plan construction workforce announced, as NBI adds new partner

    300 additional workers since January brings total workforce to over 1,500, including 80 from new build partner, Gaeltec Kilkenny-based firm, Gaeltec, now commencing work on roll-out in Wicklow National Broadband Ireland, the company delivering the National Broadband Plan, has today (Tuesday) announced that the total construction workforce delivering the roll-out has now reached over 1,500, […]

    READ MORE